Tue. 28.2.2007, 17:00 present: Riccati, Tosello, Fabjan, Riegler, Leistam, Ijzermans, taureg, Schukraft, Ake, Denarie, Nooren
SDD cable routing: Cable routing and soldering is progressing.Slower than foreseen. End of soldering not on sunday 4.3. but probably on wednesday 7.3. Leaks on the endladders confirmed. 2.5bar overpressure in 5m tube of 4mm diameter --> 62cm^3. Loss of 0.3 bars in three hours.
Strategy. Put glue on suspected leak point and repeat test. Only then a test with water. Try to find a precise manometer for faster testing.
SDD cable trays on frontabsorber: Two cable trays shipped to CERN by end of this week. Installation scheduled for Saturday March 10th.