Mon 26.2.2007, 17:00 present: Riccati, Tosello, Labbe, Fabjan, Evrard, Ijzermans, Riegler

SDD cable routing: Cable routing and soldering is progressing. No problems encountered so far. Plan is to finish cabling work on Sunday 4.3 in order to start combined test beginning of week 10. Daily updates will be done in the 17:00 meetings. Meeting with SPD people (Stefanini, Pepato) planned for tuesday 27.2. in order to verify cabling compatibility with SPD.

SDD cable trays on frontabsorber: Problem with PCBs in patchpanels discovered. Short circuit between traces. Installation on Saturday 3.3. is definitely impossible. Company checks if short can be removed with milling machine. If not -- new PCBs to be produced. New schedule to be worked out.

Russian team cabling: T0-C, V0-C cables finished. FMD-C cabling started today. To be finished by thursday 1.3.