Thu 1.2.2007, 17:00 present: Riegler, Riccati, Evrard
Outline of SDD/SSD work: Perform checks until moday 5.2. Preparation of SSD/SDD insertion on monday/tuesday. SSD/SDD insertion on tuesday/wednesday.
SDD cables have no connectors yet. A single real patchpanel will be placed in front SDD in order to determine the cable length, solder the connector boards and perform a test.
Lifting jig for ITS barrel to be checked by CERN.