Thu 18.1.2007, 17:00
Overall plan is to move the TPC by 50cm on friday. Start the TPC introduction on monday morning in order to be done on tuesday.
Things to be done on friday.
Finish survey of adjusted DF position. Install survey targets on TPC. Lower C-I SF foot by 3mm. Calibrate theodolite bracket on shielding wall. Place comparators on TPC A-side.
Want to move 50cm on late afternoon in order to be ready to start introduction on monday an finish by tuesday evening.
No TPC movement on saturday. Only preparations of necessary.