Mon, 15.1.2007, 17:00, present: Klempt, Lesenechal, Riegler, Denarie

BSF to be opened by 5mm (Labbe, tuesday) in order to avoid touching of transfer rails and BSF. DF to be fixed to concrete blocks by tuesday.

TPC rails in spaceframe were cleaned. Outer insulation gas volume was leak tested by putting gas in and observing that the output is bubbling. Drift gas volume is in any case always on 100l/h and bubbling.

Open issues before start moving of the TPC: 1) Alignment of SSW and TPC 2) Tensioning of Bretelles 3) Alignment procedure of SSW and TPC. All points to be answered by P. Glassel.

TPC will be displaced with motor pump and not with a hydraulic pump as done during the integration test. Prepared by DT1.

Probable start to move TPC is thursday or friday.