Important Dates (Planning Version 106):
SF in Final position: Mar. 28
TRD Rail Alignment: Mar. 29 - Apr. 9
Yellow Platform: Mar. 29 - Apr. 12
HMPID test: Apr. 13 - Apr. 20
Install BSF: Apr. 21 - Apr. 27
TOF/TRD insertion test: Apr. 28 - May 5
Remove yellow platform: May 8 - May 10
TOF installation tools: may 8th - May 10th
TRD installation tools: may 10th - May 12th
TOF/TRD installation: Jul. 19 - Sep. 1